Architect Evaluation

 

Proposals from 6 vendors were evaluated on March 20, 2007 by a team consisting of:

County Administrator, Sheriff, Justice Sanctions Director, Facilities Director, Finance

Director,  Purchasing Manager, and Market & Johnson. 

 

The vendors were evaluated on the following criteria.

 

Category                                              Evaluation points

                                                                   

                      Total evaluation points      150                                             

 

It was determined that the top two evaluated firms were significantly better qualified than the other firms.

 

On March 27, 2007, a joint meeting of the LEC Addition and Public Works Committees interviewed  Potter Lawson / River Architects and Venture Architects .  The twelve (12) person Evaluation Team consisted of members of the LEC Addition Committee, Public Works Committee, and County staff.

 

The vendors were evaluated on the following criteria:

 

Category

Possible points per evaluator

Possible cumulative points

Potter Lawson cumulative points

Venture Architects cumulative points

Cost

35

420

420

408

Vendors approach to project

35

420

396

363

Experience of key personnel

35

420

385

390

Vendors relevant experience

35

420

386

392

References

10

120

118

119

Total

150

1,800

1,705

1,672

 

The joint meeting recommended selecting the collaboration of Potter Lawson / River Architects for the LEC Addition project.